Your key dates, planned backward from your target delivery
One project team, every detail considered. Ours is a proven process: each step builds on the one before. We’ll work with you wherever we can while keeping quality and accuracy first.
01 Scope + Budget Alignment
Project team
Target1/28/28Fri
02 VFX
Vonmod
Target2/18/28Fri
03 Verification
Project team
Target3/10/28Fri
04 Production
Project team
Target4/14/28Fri
05 Staging and Delivery
Vonmod
Target5/26/28Fri
Dates are approximate. Lead times run 6 to 14 weeks or more, moving with Vonmod’s capacity across studio, production and install, and dates adjust for project size, holidays and circumstances beyond our control.
Signing your Back of the Envelope and paying the advance holds your place in our schedule and starts locking in your dates.
These dates sit inside our process. Each step marks a stage of how we work, from Scope + Budget Alignment through Staging and Delivery. Installation follows, based on your install option.
Custom projects take considerable time to do well. Excellence shouldn’t be rushed.
Cabinetry is one of the first things to plan and one of the last to install. Each trade depends on the one before it, so delays compound: a week lost on window installation can hold up insulation, drywall, floors and paint, and cost more than a week by the time cabinets go in.
Your builder sets the overall schedule. A remodel may come together in months; a new home can take years. Our steps fit within it.
Why dates move
Early schedules are a best guess. In our experience with highly custom projects, only about one in four keeps its first proposed schedule. When one step lands late, the steps after it move too.